New Meter Connection
Execution steps
23 steps
- 01Customer will create request along with NOC request(part of this request)
- 02Inbound integration to receive request
- 03New connection request created.
- 04SAP ISU Subscriber / Business Partner validation (Outbound)
- 05SAP ISU Subscriber / Business Partner Validation
- 06If documents are valid
- 07Reject request and inform customer through mail/SMS
- 08Temporary meter request exists
- 09Bind temporary meter number with new connection request number
- 10Issuance service and retrieve data from NOC and thermal isolation request
- 11Site Visit Appointment
- 12Validate source of supply (GIS and SAP PM)
- 13Load Study
- 14Design Preparation
- 15Prepare material and activity list
- 16Prepare material and activity list
- 17Customer Funded?
- 18Customer Funded – Meter Sub Process
- 19Outbound Integration Send For Design Approval
- 20Check approval authority
- 21In bound Integration to get approval authority data
- 22Cost Approved by SEC
- 23Work Order Execution
Data requirements
17 requirements
- Subscriber / Customer RecordrequiredCustomer
The applicant must exist (or be created) as a validated subscriber before connection.
- Service Location / Premise Recordrequired
The premise/service point must be defined for the new connection.
- Meter Inventory PartrequiredInventory Part
New meter models and connection materials must exist as inventory parts.
- Work Type (New Connection)required
A new-connection work type drives intake, study and installation routing.
- Technician ResourcerequiredResource
Field resources perform the site visit and installation.
- Connection Fee Price Basic Datarecommended
Standard connection fees support cost estimation and payment confirmation.
- SAP ISU Integration Mappingrecommended
The new device and contract must be created in SAP ISU after installation.
- CompanyrequiredCompany
Company context underpins requests, work orders and fee postings.
- SiterequiredSite
Connection work orders and meter stock transactions execute at a site.
- Case / Request Type (New Connection)required
Classifies the request and drives new-connection workflow routing.
- Mobile User Accountrequired
Technicians need mobile users for site visit and execution steps.
- GIS Facility Recordrecommended
New service point must be created/reflected in GIS network data.
- Tariff / Capacity Class Codesrequired
New connection must be assigned the correct tariff/capacity class.
- Approval Matrix / Authorization Rulesrequired
Technical study and cost approvals require authorization limits.
- Rejection / Cancellation Reason Codesrecommended
Standardizes rejection outcomes at validation and study steps.
- Number Series (Request/Work Order)recommended
Ensures unique identifiers for requests and generated work orders.
- Site Visit Checklist / eForm Templaterecommended
Structured capture of site and technical study findings.
Configuration decisions
3 decisions
- Define approval-authority thresholds and cost-approval routing (e.g. SEC) for New Meter Connection.
- Configure FSM Connect intake channels and SAP ISU subscriber/business-partner validation mapping.
- Set up GIS material and activity list capture and unit-rate cost retrieval for Field Service & Mobile.
KPIs
3 measures
- Average cycle time from request creation to work-order execution.
- Percentage of requests validated/approved without rework or remarks.
- Cost-approval turnaround time (design to SEC approval).
Integration points
9 integrations
- Integration/interaction with FSM within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with FSM Connect within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with FSM Mobile within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with GIS within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with IFS within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with SAP ISU within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with SAP-HR within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with SAP-MM within the New Meter Connection planning flow (swimlane system).
- Integration/interaction with System Construction within the New Meter Connection planning flow (swimlane system).
Prerequisites
3 prerequisites
- Active SAP ISU subscriber / business partner record for validation.
- FSM, FSM Connect and FSM Mobile integration channels configured and operational.
- GIS design and unit-rate cost catalog available for material and activity lists.
Industry variants
1 variant
- electric utility
Electric distribution utility To-Be variant of New Meter Connection as modeled in the client draw.io planning flows (FSM + SAP ISU + GIS).
Process diagram
1 BPMN diagram
A real BPMN diagram, editable in the platform, not a picture of one. It is the same diagram your team will annotate in the workshop.
Sources
1 citation
Where this came from. Every process traces back to IFS documentation and release notes, so a claim about how IFS behaves can be checked rather than believed.
This is one of 620.
The rest of the library is worked to the same depth. A license opens all of it, and your own repository is cut from it.